Draw, Fabricate, Supply, Deliver, Replace, and Install new pipework with fittings inside the cable tunnels and pipe trenches at Kriel Power Station for a…
ESKOM
State-owned company · Tender (request for bid) · Mpumalanga · Tender no. E2902GXMPKRI
13 days left
Closes: Friday, 11 December 2026 at 10:00 SAST
Requirements, and how we know them
- CIDB grade 7 or higher (Read from official document)
- Tender documents (Not confirmed)
- CSD registration (General guidance)
- Valid tax compliance status (General guidance)
- Standard SBD forms (General guidance)
Find it on eTenders: search for E2902GXMPKRI
Official documents
- 240-12248652_List of Tender Returnables_Cat 3_ Rev 7.pdf
- 240-68099512 Form A_Cat 3_ Rev 9.pdf
- 240-105658000 Supplier Quality Management Specification.pdf
- 240-109253698 CQP Template 2021.pdf
- Affidavit Example (1).pdf
- Annexure B.pdf
- Draw Fabricate Supply Deliver Replace and Install New Pipework with Fittings_Technical Evaluation Strategy.pdf
- Eskom - Standard Conditions of Tender - 30 January 2025.pdf
- Eskom_Supplier_Integrity_Pact_-_02_June_2023.pdf
- ITT_CIDB Ann G Compulsory Enterprise Questionnaire.pdf
- ITT_CIDB SBD4 SCM_declaration_interest_SBD4_.pdf
- ITT_CIDB SBD9 SCM_certificate_independent_bid_determination_SBD9_.pdf
- ITT_CIDB Standard Conditions of Tender Ann.pdf
- RER0371 - Environmental Evaluation - Draw Fabricate Supply Deliver Replace and Install New Pipework with Fittings inside the Cable Tunnels and Pipe Trenches.pdf
- Safety file checklist.pdf
- SHE Requirement (1).pdf
- SHE SPEC.pdf
- Notification NR 1 - ITT and NEC uploaded.pdf
- CONFIRMATION OF EMPLOYMENT EQUITY.pdf
- NEC3 TSC_New Pipework.pdf
- Notification NR 2 - Site Visit and PPE Requirements.pdf
- 0.45-61012-01 FIRE PROTECTION SYSTEM EMULSIFIER FIRE SYSTEM-SERVICES PUMP HOUSE.pdf
- 0.45-61012-02 FIRE PROTECTION SYSTEM EMULSIFIER FIRE SYSTEM- SERVICES PUMP HOUSE TO CHEMICAL HOUSE.pdf
- 0.45-61012-03 FIRE PROTECTION SYSTEM EMULSIFIER FIRE SYSTEM -CHEMICAL HOUSE TO UNIT 1.pdf
- 0.45-61012-04 FIRE PROTECTION SYSTEM EMULSIFIER FIRE SYSTEM UNIT 1 TO 3.pdf
- 0.45-61012-05 FIRE PROTECTION SYSTEM EMULSIFIER FIRE SYSTEM UNIT 4 TO 6.pdf
- 0.45-61012-05 FIRE PROTECTION SYSTEM EMULSIFIER FIRE SYSTEM UNIT 4 TO 6.zip
- 0.45-61012-06 FIRE PROTECTION SYSTEM EMULSIFIER FIRE SYSTEM UNIT 6 TO CABLE TRENCH.pdf
- 0.45-61012-07-Emulsifier-Unit 6 Cable Tunnel.pdf
- 0.45-61012-08-Emulsifier-Unit 5 Cable Tunnel.pdf
- 0.45-61012-09-Emulsifier-Unit 4 Cable Tunnel.pdf
- 0.45-61012-10-Emulsifier-Unit 3 Cable Tunnel.pdf
- 0.45-61012-11-Emulsifier-Unit 2 Cable Tunnel.pdf
- 0.45-61012-12-Emulsifier-Unit 1 Cable Tunnel.pdf
- 0.45-61012-13-Emulsifier-Cable Tunnel-Bridge By Chemical House.pdf
- 0.45-61011-01 FIRE PROTECTION SYSTEM HYDRANT FIRE SYSTEM RAW WATER PUMP HOUSE.pdf
- 0.45-61011-02 FIRE PROTECTION SYSTEM HYDRANT FIRE SYSTEM -RAW WATER TO EMULSIFIER PUMP HOUSE.pdf
- 0.45-61011-03 FIRE PROTECTION SYSTEM HYDRANT FIRE SYSTEM -RAW WATER TO EMULSIFIER PUMP HOUSE.pdf
- 0.45-61011-04 FIRE PROTECTION SYSTEM HYDRANT FIRE SYSTEM -RAW WATER TO EMULSIFIER PUMP HOUSE..pdf
- 0.45-61011-05 FIRE PROTECTION SYSTEM HYDRANT FIRE SYSTEM -CHEMICAL HOUSE TO BRIDGE.pdf
- 0.45-61011-06 FIRE PROTECTION SYSTEM HYDRANT FIRE SYSTEM -UNIT 1 TO 3.pdf
- 0.45-61011-07 FIRE PROTECTION SYSTEM HYDRANT FIRE SYSTEM -UNIT 1 TO 3.pdf
- 0.45-61011-09 FIRE PROTECTION SYSTEM HYDRANT FIRE SYSTEM -UNIT 6 TO CABLE TRENCH.pdf
- 0.45-61011-10-Hydrant-Unit 6 Cable Tunnel.pdf
- 0.45-61011-11-Hydrant-Unit 5 Cable Tunnel.pdf
- 0.45-61011-12-Hydrant-Unit 4 Cable Tunnel.pdf
- 0.45-61011-13-Hydrant-Unit 3 Cable Tunnel.pdf
- 0.45-61011-14-Hydrant-Unit 2 Cable Tunnel.pdf
- 0.45-61011-15-Hydrant-Unit 1 Cable Tunnel.pdf
- 0.45-61011-16-Hydrant-Cable Tunnel-Bridge By Chemical House.pdf
- 0.45-61010 - 01 FIRE PROTECTION SYSTEM HYDARNT & EMULSIFIER PLOT PLAN.pdf
- Clarification NR 2 - Answers to clarification questions.pdf
- Clarification NR 2 - Answers to clarification questions.pdf
- Notification NR 3 - Tender Extension.pdf
Official contact
Phumelele Mncwango · mncwanpj@eskom.co.za · 017-648-0119
Before you submit
- Sign every SBD form
Usually SBD 1, SBD 3.1, SBD 4 and SBD 6.1, as issued in this tender pack. One unsigned form can disqualify the bid; the signatory must be authorised to sign for the business. - Tax compliance status valid on the closing date
Check it on SARS eFiling before 11 Dec 2026. A status that lapses before closing can cost you the award. - CSD profile compliant, details matching
Your CSD record should show as compliant, with the same name, registration number and directors as CIPC, SARS and your B-BBEE documents. - Proof for every point you claim
Your B-BBEE affidavit or certificate, and anything else the SBD 6.1 asks for, must support the specific-goal points you claim. - CIDB grade 7 or higher
Active on the CIDB register on the closing date, or through a joint venture that meets the grade. - The buyer's pricing schedule, complete
Use the schedule exactly as issued, fill in every line, and check whether prices must include VAT. - Every returnable schedule
List the returnable documents from the tender pack itself and tick them off, rather than relying on your last bid. - Submit a day early
Late bids aren't considered, even by a minute. Aim to submit by 10 Dec 2026, and check the address or upload method twice.