Requirements, and how we know them
- CIDB grade 7 or higher (Read from official document)
- Tender documents (Not confirmed)
- CSD registration (General guidance)
- Valid tax compliance status (General guidance)
- Standard SBD forms (General guidance)
Find it on eTenders: search for E2737GXMPKRI
Official documents
- Affidavit Example (1).pdf
- Annexure C.pdf
- Eskom - Standard Conditions of Tender - 30 January 2025.pdf
- Technical Strategy for the Refurbishment of Boiler and Turbine Isolating valves at Kriel Power Station_SOW Upload.pdf
- Affidavit Example.pdf
- Annexure D.pdf
- Annexure E.pdf
- Eskom - Standard Conditions of Tender - 30 January 2025.pdf
- Eskom_Supplier_Integrity_Pact_-_02_June_2023.pdf
- E-Tenderers E-Tendering Training Acknowledgement Form.docx
- eTendering_ExternalUser_Guide_Final (8).pdf
- Guidance document to fill in local content.pdf
- 240-105658000 Supplier Quality Management Specification (3).pdf
- SHE SPECIFICATION.pdf
- Environmental Requirement Form - Boiler and turbine valves.pdf
- 240-12248652_List of Tender Returnables_Cat 2_ Rev 7.pdf
- 240-68099512 Form A_Cat 2_ Rev 9.pdf
- 240-109253302 _ Quality Control Plan or Inspection Test Plan (QCP or ITP) rev 2.pdf
- 240-109253698 CQP Template 2021.pdf
- Annexure B.pdf
- OHS requirement.pdf
- Safety file checklist.pdf
- TEC for Refurbishment of Boiler and Turbine Isolating valves during outages at Kriel Power Station_R2.pdf
- Clarification Meeting Minutes13 April 2026.pdf
- Notification NR1 Clarification 1.pdf
- Notification NR2.pdf
Official contact
Phumelele Mncwango · mncwanpj@eskom.co.za · 017-648-0119
Before you submit
- Sign every SBD form
Usually SBD 1, SBD 3.1, SBD 4 and SBD 6.1, as issued in this tender pack. One unsigned form can disqualify the bid; the signatory must be authorised to sign for the business. - Tax compliance status valid on the closing date
Check it on SARS eFiling before 11 Dec 2026. A status that lapses before closing can cost you the award. - CSD profile compliant, details matching
Your CSD record should show as compliant, with the same name, registration number and directors as CIPC, SARS and your B-BBEE documents. - Proof for every point you claim
Your B-BBEE affidavit or certificate, and anything else the SBD 6.1 asks for, must support the specific-goal points you claim. - CIDB grade 7 or higher
Active on the CIDB register on the closing date, or through a joint venture that meets the grade. - The buyer's pricing schedule, complete
Use the schedule exactly as issued, fill in every line, and check whether prices must include VAT. - Every returnable schedule
List the returnable documents from the tender pack itself and tick them off, rather than relying on your last bid. - Submit a day early
Late bids aren't considered, even by a minute. Aim to submit by 10 Dec 2026, and check the address or upload method twice.