Request for proposal (RFP) for refurbishment and upgrade of electrical systems at megawatt park
ESKOM
State-owned company · Request for proposal (RFP) · Gauteng · Tender no. E3865EGDMWP
12 days left
Closes: Thursday, 10 December 2026 at 10:00 SAST
Requirements, and how we know them
- CIDB grade 7EP or higher (Read from official document)
- Reserved for EME and QSEs (Read from official document)
- At least 70% on functionality (Read from official document)
- Tender documents (Not confirmed)
- CSD registration (General guidance)
- Valid tax compliance status (General guidance)
- Standard SBD forms (General guidance)
Find it on eTenders: search for E3865EGDMWP
Official documents
- MWP_Electrical System upgrade_NEC_Final.pdf
- MWP-ELECTRICAL REFURBISHMENT-ACTIVITY SCHEDULE R.3.xlsx
- MWP_Electrical System upgrade_NEC_Final.docx
- Request for Proposal (RFP)_Refurbishment and Upgrade of Electrical Systems at Megawatt Park E3865EGDMWP (003).pdf
- SDLI Stratgey Refurbishment and Upgrade of Electrical Systems at Megawatt Park.pdf
- 20261110_Cat2- Quality Req _MWP Refurbishment of Electrical Systems .pdf
- 240-105658000 SUPPLIER QUALITY MANAGEMENT SPEC REV4 FINAL 2026.pdf
- 20261110_ Form A Cat2_ MWP Refurbishment of Electrical Systems .pdf
- 240-109253302 _ Quality Control Plan or Inspection Test Plan (QCP or ITP) rev 2.docx
- 240-109253698 Contract Quality Plan (CQP) Template.docx
- 20260824_GFD_ERE_MWP_Electrical Systems SHE Specification_Rev01.pdf
- 20260828_GFD_ERE_MWP_Electrical Systems Project Occupational Health and Safety Risk Assessment_Rev01.xlsx
- Annexure B_Acknowledgement Form for Eskom SHE Rules and other Requirements (5).pdf
- 20260825_GFD_ERE_MWP_Electrical Supply Project_SHE Tender Evaluation.pdf
- MWP Replacament of main Electrical Systems Technical Evaluation Strategy Report Rev 1 Final.pdf
- Appendix C1 _ Phase 1 _ MWP_Preliminary Short_Circuit _ Summary.pdf
- Appendix B _ Phase 1 _ MWP_Preliminary Load_Flow Report.pdf
- Appendix A13 _ Compliance Schedule.xlsx
- Appendix A8.1 _ Diesel Generators preliminary sizing schedule AB _ Block A and B.docx
- Appendix A5_ Transformers - Technical Schedule AB Rev 1.docx
- Appendix A1.1 _ MWP MV Exiting Single Line Drawing 0.50-2001 11kV Phase 1 and 2 to be updated.pdf
- 363-ERE-CBBZ18-PN0017-59 MWP Refurbishment Project Electrical Requirements _ Rev 3.2 Final.pdf
- Scope of Work-Replacement of MV Incomer Cables (003) Signed.pdf
- Appendix A2 and A3_ 11kV MWP SWITCHGEAR SCHEDULE REV 3.1.xlsx
- 230311-E-E-200-E_rev0_(Generator Plant - Fuel Line Layout).pdf
- Appendic A6.1 _ List of LV Boards _ 240-56356465 Rev 2.xls
- MWP_Electrical System upgrade_NEC_23 Nov 2026 Rev2.pdf
- MWP_Electrical System upgrade_NEC_23 Nov 2026 Rev2.docx
Official contact
Martin Nndwammbi · nndwamtm@eskom.co.za · 011-800-5234
Before you submit
- Sign every SBD form
Usually SBD 1, SBD 3.1, SBD 4 and SBD 6.1, as issued in this tender pack. One unsigned form can disqualify the bid; the signatory must be authorised to sign for the business. - Tax compliance status valid on the closing date
Check it on SARS eFiling before 10 Dec 2026. A status that lapses before closing can cost you the award. - CSD profile compliant, details matching
Your CSD record should show as compliant, with the same name, registration number and directors as CIPC, SARS and your B-BBEE documents. - Proof for every point you claim
Your B-BBEE affidavit or certificate, and anything else the SBD 6.1 asks for, must support the specific-goal points you claim. - CIDB grade 7EP or higher
Active on the CIDB register on the closing date, or through a joint venture that meets the grade. - Proof you're an EME or QSE
This tender is reserved. Include the affidavit or certificate that shows your business size. - Reach 70% on functionality
Bids below the threshold aren't scored on price. Include every CV, reference letter and method statement the scoring table asks for. - The buyer's pricing schedule, complete
Use the schedule exactly as issued, fill in every line, and check whether prices must include VAT. - Every returnable schedule
List the returnable documents from the tender pack itself and tick them off, rather than relying on your last bid. - Submit a day early
Late bids aren't considered, even by a minute. Aim to submit by 09 Dec 2026, and check the address or upload method twice.